Update 6/6/25 – Sewer work is scheduled for the week of Monday, June 9, 2025. Our contractor will be installing new sewer lines on Rangeway Road starting at the Route 3 overpass ending at 222 Rangeway Road. Rangeway Road will be limited to local traffic only between 159-222 Rangeway Road. Southwest bound traffic will be redirected via Boston Road, Bridge Street, Treble Cove Road to Nashua Road, while Northeast bound traffic will be redirected via Nashua Road, Treble Cove Road, Bridge Street to Boston Road. Work hours are from 7:30am to 4pm.

—————-

Update 6/2/25 – Rangeway Road Sewer Construction- Blasting is scheduled to begin on June 3rd and will continue for approximately 2 weeks. Rangeway Road is closed between Sterling Road and the Route 3 overpass. Detours will be in place and officers will be on site to direct traffic as needed. Residents, school buses and businesses will have full access with minor delays.